AG2-A2.1 Monitoring Campaign-Synthesis

According to the activities proposed by GAF, the monitoring activity is a nodal point of the project. The performances of the devices purchased for the CRIMIGE Center are thus tested, but the impact of the electricity production and distribution activities on the environment in the cross-border area is measured.

Within the project Time Plan, 3 monitoring campaigns were foreseen, distributed, as far as possible, in different seasons.

  1. The 1st stage – 4 months, June-September 2020, after the end of the equipment acquisition activity, the documentation and establishment of the itinerary period – the hot season, late summer-autumn is targeted.
  2. The 2nd stage – 3 months, December 2020-February 2021– the cold season is targeted.
  3. The 3rd stage – 3 months, April-June 2021 – an intermediary season is targeted, more precisely spring-early summer.

The following types of installations within the impact area:

•                      Level 1 -Euro-regional

•                      Level 2 – Regional-national with cross border impact

•                      Level 3 –Community level (local)

  • Electric stations (ST).

•          Electrical transmission networks / transmission lines (RET).

•          Power plants.

•          Broadcast relays for mobile telephony.

Biological systems

•                      Habitat investigations

                                   The vegetation cover/carpet

•                      Electric transmission networks / transmission lines (RET)

o                                 Species of avifauna interest”